HI-ECN3 - Target Complex and surface building - preliminary hazard identification

Submitted by ogomezal on

Following up from the surface building integration meeting last week, 22nd of May, let’s meet to start the preliminary hazard identification related to:

 

  1. Cooling and ventilation system
  2. Target cooling process
  3. Target material selection
  4. Target dismantling process
  5. CV technical room.

 

The idea is also to optimize the building layout so to separate the process risks from the ones related to ancillary equipment/services.

Type
Meeting
Timezone
Europe/Zurich
Location
CERN
Room
864/2-D17
Category
HI-ECN3 Project Safety Reviews / Meetings